First Two Portside Sponsons Installed on Costa Concordia Offshore Giglio Island

First Two Portside Sponsons Installed Offshore Giglio Island

On April 17th, the positioning of the first portside sponson (p10) has been succesfully completed at the site of Costa Concordia wreck.

Operations have continued yesterday with installation of the second sponson (p11) offshore Giglio Island.

Eventually, the sponsons will be welded on the hull of the wreck . At the same time, drillings for next 10 underwater holes will be undergoing in order to position remaining platforms 2 & 3.

[mappress]
April 19, 2013