Foundations Fabrication for Gode Wind OWF Well on Its Way

The fabrication of the Gode Wind foundations, which Bladt Industries are fabricating for Dong Energy, is well on the way.

Foundations Fabrication for Gode Wind OWF Well on Its Way
The Gode Wind mockup at Bladt Industries upending site.

This week the TP mockup was upended at Bladt’s upending site. After this, the Bladt team installed the concrete platform on the TP mockup, which is the first of 97 TP’s for the Gode Wind project.

The Bladt team is working intensely on the Gode Wind foundations – the first shipments of plates have arrived and the welders are working on rolling the plates. The project is expected to be ready for handover in the fall of 2015.

Press Release, June 13, 2014