Load Out of Borkum Riffgrund 1 Foundations Underway

Load Out of Borkum Riffgrund 1 Foundations Underway

On December 26th the first loadout of the Borkum Riffgrund 1 foundations took place.

This week another 4 monopiles, 4 transition pieces and 4 anode cages – four complete foundations – were loaded onto the ship and headed for their destination in Eemshaven, Germany.

Next load out is expected to take place next weekend. Bladt Industries expects to have shipped all 77 foundations by august 2014.

[mappress]

Press release, January 10, 2014; Image: Bladt