2630 results found for 'nord stream'

2630 results found for 'nord stream'
Order results by

A list of search results

  • 12 April 2018
    Business & Finance, Operations & Maintenance

    Project developer Nord Stream 2 AG said it has received the second of two permits required to construct and operate the planned natural gas pipeline in the Finnish Exclusive Economic Zone (EEZ), completing the permitting procedure in Finland. The permit was granted by the Regional State Administrative Agency Southern Finland in accordance with the Water […]

  • 15 April 2019
    Operations & Maintenance

    Danish Energy Agency (DEA) has received an additional application from Nord Stream 2 AG for permission to construct transit pipelines south of Bornholm on the continental shelf. The application is accompanied by an environmental impact assessment with a number of annexes in order to assess possible environmental impacts in Denmark or cross-border environmental impacts from […]

  • 25 April 2017
    Business & Finance, Operations & Maintenance

    Nord Stream 2 AG has signed financing agreements for the Nord Stream 2 pipeline project with ENGIE, OMV, Shell, Uniper and Wintershall. These five European energy companies have committed to provide long-term financing for 50 % of the total cost of the project, which is currently estimated to be €9.5 billion. Each European company will […]

  • 11 January 2018
    Equipment

    Halfwave has been awarded a contract to design and build 48” Acoustic Resonance Technology (ART) Scan in-line inspection tools for Nord Stream 2. The ART Scan tools will be used to inspect the 48” Nord Stream 2 twin gas pipelines in the Baltic Sea. Halfwave’s custom-build ART Scan tools will be used to inspect the […]

  • 18 May 2017
    Business & Finance, Operations & Maintenance, Project & Tenders

    MMT Sweden has been awarded a three-year contract by Nord Stream AG to inspect both lines of the Nord Stream pipeline running through the Baltic Sea from Russia to Germany. The external inspection of the pipeline will be executed by the joint venture between MMT Sweden and Reach Subsea. The scope of work, involving approximately […]

  • 13 December 2011

    From 13 December  to 15 December, the gas flow through the Nord Stream Pipeline will be temporarily suspended due to planned maintenance works at Gazprom’s connecting pipeline. During the shutdown time, Nord Stream will also carry out maintenance activities at the installations on the German landfall. In particular, the shutdown valves and the fire and […]

  • 24 May 2012
    Business & Finance, Operations & Maintenance

    As part of the ongoing ramp-up phase and as preparation for the operation of Nord Stream as a twin-pipeline gas transportation system, Nord Stream AG is conducting load tests for Line 1. Over the past three days Line 1 has been operating at full capacity of app. 75 million cubic meters per day which corresponds […]

  • 7 February 2014

    Alexey Miller of Gazprom and Matthias Warnig, Managing Director of Nord Stream met in Moscow where they addressed the possibility of building up capacities of the Nord Stream gas transmission system via the Baltic Sea by constructing one or two additional strings. Gazprom reviewed the results of the feasibility study performed by the Nord Stream […]

  • 1 February 2017

    Following the initial rejection of the logistics support by Sweden to Wassco for the Nord Stream 2 pipeline project, things have seemingly changed. To remind, reports in 2016 said that the authorities of the Swedish Region Gotland and the municipality Karlshamn had decided not to sign an agreement for the utilization of their respective harbours – […]

  • 28 February 2012

    Nord Stream AG said it has won the inaugural “Pipeline Project of the Year” award at the 2012 European Gas Conference. The award, which was presented by The Energy Exchange in conjunction with Natural Gas Europe, recognises Nord Stream’s achievement in starting to make its contribution to energy security in the European Union on time […]

  • 20 April 2016

    Austria’s Voestalpine has said it has secured a major contract supporting the construction of the the Gazprom-run Nord Stream 2 pipeline project between Europe and Russia. The Austrian company supplied 170,000 tonnes linepipe plates for the first part of the offshore gas pipeline in the Baltic Sea between 2008 and 2010. Under the new contract, the […]

  • 12 December 2018
    Business & Finance, Equipment, Operations & Maintenance

    Allseas’ pipelay vessel Pioneering Spirit will enter the Baltic Sea via the Great Belt Bridge in Denmark to join the Nord Stream 2 construction fleet. The vessel is due to start the pipe-laying in the Finnish Exclusive Economic Zone (EEZ) in the coming week. Pioneering Spirit will be mobilised in Denmark for a few days, […]

  • 23 May 2019

    Russian giant Gazprom held gas discussions with OMV discussing exports of natural gas to Austria as well as the implementation of Nord Stream 2 project. 

  • 25 April 2012
    Business & Finance, Operations & Maintenance

    Nord Stream AG announces the successful completion of its complex international logistics programme. This award-winning green logistics concept enabled the most efficient and environmentally-sound way of supplying to the pipe-laying vessels the 200,000 24-tonne concrete weight coated (CWC) pipes needed for Nord Stream’s twin natural gas pipelines through the Baltic Sea. Twelve-tonne steel pipes were […]

  • 7 July 2011
    Business & Finance

    The latest results from Nord Stream’s environmental monitoring programme in the Swedish Exclusive Economic Zone, EEZ show that the company has complied with and even exceeded the conditions in the permit granted by the Swedish government. Calculations and models in Nord Stream’s Environmental Study have proven accurate, and it is now estimated that the environmental […]

  • 13 April 2012
    Business & Finance

    Nord Stream is entering an intensive period during which its engineers and partners will take key steps towards completing the integrated twin pipeline system capable of transporting up to 55 billion cubic metres (bcm) of Russian gas a year to Europe through the Baltic Sea, for at least 50 years: control systems will be adapted to integrate the twin pipelines into a single automated twin-pipeline gas transport system, at the same time as pipe-laying of the second pipeline is completed and pre-commissioning started.

  • 4 June 2021
    Business Developments & Projects, Collaboration, Project & Tenders

    Russia has finished laying the first line of the Nord Stream 2 gas pipeline to Germany, Reuters reported President Vladimir Putin as saying at an economic forum on Friday, 4 June. Nord Stream 2 comprises two parallel 48-inch lines, approximately 1,200 kilometers long, each starting southwest of St. Petersburg and ending at Greifswald on the […]

  • 13 April 2011

    Construction of the Nord Stream natural gas pipeline through the Gulf of Finland isn’t having a major impact on the environment, the Estonian government said. Russia aims to diversify its European transit options through Nord Stream. The dual pipeline will run from the shores of the Gulf of Finland through the Baltic Sea to Germany. […]

  • 10 February 2011
    Business & Finance

      Nord Stream has won the award for European mid-stream gas project of the year at this year’s Project Finance Awards ceremony. The awards recognise innovation, deal repeatability, best practice, problem solving, risk mitigation, value for money and speed of delivery in financing. Nord Stream was singled out in particular for the fact that 2.5 […]

  • 7 February 2024
    Authorities & Government, Business & Finance, Business Developments & Projects, Collaboration, Infrastructure, Project & Tenders, Regulation & Policy, Safety

    Sweden has decided to close its investigation concerning the explosions on the Nord Stream 1 and 2 gas pipelines that occurred in September 2022. Germany, Sweden and Denmark each initiated respective national investigations into the incident after four gas leaks were found on the Nord Stream 1 and 2 pipelines in September 2022, two in Sweden’s exclusive economic […]

  • 27 April 2010

    The Nord Stream consortium has contracted the Dutch joint venture Boskalis-Tideway Offshore for post-lay rock placement. Work on the $133-million contract is due to start in 2011 and should be completed in 2012. Various pipelay contractors are installing the Nord Stream trunklines, which will take gas from fields in northern Russia through the Baltic Sea […]

  • 15 April 2019

    Nord Stream 2 AG has submitted a third application for a route through Danish waters and accused Denmark of deliberately attempting to delay the project.

  • 9 February 2011

      Nord Stream has won the award for European mid-stream gas project of the year at this year’s Project Finance Awards ceremony. The awards recognise innovation, deal repeatability, best practice, problem solving, risk mitigation, value for money and speed of delivery in financing. Nord Stream was singled out in particular for the fact that 2.5 […]

  • 26 September 2012

    Alexey Miller, Chairman of the Gazprom Management Committee and Kurt Bock, Chairman of the Board of Executive Directors of BASF held a working meeting at the Gazprom headquarters. Different aspects of cooperation in the oil and gas sector were addressed in the course of negotiations. The parties have discussed the progress with execution of two […]

  • 7 October 2009

    Finland, which earlier raised environmental concerns over the construction of the Nord Stream gas pipeline across the Baltic Sea, is set to give its approval to the project, a Belgian radio station reported on Wednesday. The Brussels-based radio station Contact said that Finland’s Minister of European and Migration Affairs Astrid Thors expected his country to […]