Tyra II; Source: BlueNord

TotalEnergies’ giant natural gas field in North Sea on track to come online this spring

With finishing touches underway, France’s TotalEnergies and its partners in the Danish Underground Consortium (DUC) are getting ready to bring on stream the Tyra II redevelopment project in the Danish sector of the North Sea in March 2024. This is said to be Denmark’s largest natural gas field.

Tyra II; Source: BlueNord

The Danish Underground Consortium (DUC) is a partnership between TotalEnergies (operator, 43.2%), BlueNord (36.8%), and Nordsøfonden (20%). While disclosing the progress made in the final stage of the Tyra redevelopment project, BlueNord confirmed the expected timeline for the first gas, referring to the REMIT notification issued by TotalEnergies.  

According to the company, significant work scope on the completion of the Tyra II facilities has been executed since October 2023. The leak testing – essential to the safety and integrity before gas-in and the functional testing of key process machinery required for processing the gas – is progressing well while the Tyra East riser platform Echo was declared hot, with all pipelines connected.

Furthermore, the de-isolation of these pipelines, which is ongoing, is seen as an important step towards first gas. More progress is also evidenced on Tyra West, as the first wells have been unplugged and de-watered, with two wireline teams working in parallel on the Tyra West B and C platforms with the unplugging of wells.

“An extensive amount of work has been carried out on the leak testing of the facilities and it is expected that all leak testing will be completed ahead of first gas export which could support an efficient ramp-up and a reduced ramp-up period. The key focus before the first gas export remains to ensure that the safety and emergency systems are fully functional,” highlighted BlueNord.

Based on TotalEnergies’ REMIT notification from January 22, the project progress to date indicates that the current restart date of March 31, 2024, remains valid. However, depending on the project’s progress, it could be reached earlier in March.

In addition, the French oil major reveals that the outcome of tests now suggests that a ramp-up to maximum technical capacity is expected to take four months from restart. Once on stream, Tyra II is expected to deliver 2.8 billion cubic meters of gas per year, which amounts to 80% of the forecasted Danish gas production.

Tyra has been a center for processing and exporting more than 90% of the natural gas produced in the Danish North Sea before its redevelopment, which was required due to the field’s natural subsidence of the chalk reservoir after many years of production.

The redevelopment entailed three elements, including decommissioning and recycling of the old Tyra platforms, recycling and extending the current platform legs on six of the platforms, which got new topsides, a completely new process module, and a new accommodation platform.

crane was put on the process module (TEG) into permanent use after the installation of the Tyra II process module in early October 2022, which broke the world record as the heaviest crane lift ever undertaken at sea. The TEG enabled the completion of the remaining scope of the hook-up, commissioning, and start-up of the project.

This process module will be able to process 300 million standard cubic feet of gas per day at peak from Tyra and five unmanned satellite fields, including Tyra SoutheastHaraldValdemarSvend, and Roar. Recently, a final investment decision (FID) was taken to drill a well in the Harald East area.

Related Article

If the drilling activities turn out to be successful, gas will be exported through the Tyra East facilities. The well could deliver production by the end of 2024.

ADVERTISE ON OFFSHORE ENERGY

𝐃𝐨 𝐲𝐨𝐮 𝐰𝐚𝐧𝐭 𝐭𝐨 𝐠𝐫𝐚𝐛 𝐭𝐡𝐞 𝐚𝐭𝐭𝐞𝐧𝐭𝐢𝐨𝐧 𝐨𝐟 𝐲𝐨𝐮𝐫 𝐭𝐚𝐫𝐠𝐞𝐭 𝐚𝐮𝐝𝐢𝐞𝐧𝐜𝐞 𝐢𝐧 𝐨𝐧𝐞 𝐦𝐨𝐯𝐞? 𝐋𝐨𝐨𝐤 𝐧𝐨 𝐟𝐮𝐫𝐭𝐡𝐞𝐫 𝐭𝐡𝐚𝐧 𝐎𝐟𝐟𝐬𝐡𝐨𝐫𝐞 𝐄𝐧𝐞𝐫𝐠𝐲! 𝐎𝐮𝐫 𝐜𝐨𝐧𝐭𝐞𝐧𝐭 𝐢𝐬 𝐫𝐞𝐚𝐝 𝐛𝐲 𝐭𝐡𝐨𝐮𝐬𝐚𝐧𝐝𝐬 𝐨𝐟 𝐩𝐫𝐨𝐟𝐞𝐬𝐬𝐢𝐨𝐧𝐚𝐥𝐬 𝐞𝐧𝐠𝐚𝐠𝐞𝐝 𝐢𝐧 𝐨𝐢𝐥 & 𝐠𝐚𝐬, 𝐦𝐚𝐫𝐢𝐭𝐢𝐦𝐞, 𝐨𝐟𝐟𝐬𝐡𝐨𝐫𝐞 𝐰𝐢𝐧𝐝, 𝐠𝐫𝐞𝐞𝐧 𝐦𝐚𝐫𝐢𝐧𝐞, 𝐡𝐲𝐝𝐫𝐨𝐠𝐞𝐧, 𝐬𝐮𝐛𝐬𝐞𝐚, 𝐦𝐚𝐫𝐢𝐧𝐞 𝐞𝐧𝐞𝐫𝐠𝐲, 𝐚𝐥𝐭𝐞𝐫𝐧𝐚𝐭𝐢𝐯𝐞 𝐟𝐮𝐞𝐥𝐬, 𝐬𝐡𝐢𝐩𝐩𝐢𝐧𝐠, 𝐚𝐧𝐝 𝐨𝐭𝐡𝐞𝐫 𝐢𝐧𝐝𝐮𝐬𝐭𝐫𝐢𝐞𝐬 𝐨𝐧 𝐚 𝐝𝐚𝐢𝐥𝐲 𝐛𝐚𝐬𝐢𝐬.

Follow Offshore Energy’s Fossil Energy market on social media channels: