VIDEO: Canyon Offshore Publishes Case Study on T1200 Sheringham Shoal Offshore Cable Trenching

VIDEO: Canyon Offshore Publishes Case Study on T1200 Sheringham Shoal Offshore Cable Trenching

In August 2012, Helix Energy Solutions Group Inc.’s robotics subsidiary, Canyon Offshore Limited (U.K.), was contracted to conduct trenching operations with the T1200 water-jet trenching system in the Sheringham Shoal offshore wind farm off the coast of the United Kingdom. The scope of work comprised of trenching of the inter-array cables with an approximate total length of 100km.

Canyon Offshore Limited (U.K.) completed the Sheringham Shoals project in a 62 day period that spanned from early July to September. The overall distance trenched was 49.97km, with an average of .805km trenched per day.

On its first dive, T1200 spent more than 30 consecutive hours on the bottom in trenching mode and only spent a total of 14.44 hours on downtime, equating to just 1.74% of the whole project.

The burial achieved during the project varied depending on the product. For the Infield Cable Type 1 400mm² a minimum depth of cover of 0.8m was achieved. For the Infield Cable Type 2 185mm² a minimum depth of cover of 0.5m was achieved. Readings of the burial were taken every two hours during the trenching of the project.

The Sheringham Shoal wind farm is located 20km off the Norfolk coastline in approximately 20m of water.

Entire Case Study


View on Youtube.

[mappress]
Press Release, February 07, 2013