Aibel Inks Gudrun Deal

Aibel has been awarded the FEED contract for Gudrun Phase 2 Water Injection.

CEO Mads Andersen signed the contract; Photo Aibel

The contract with Equinor also includes an option for the actual implementation (EPCI).

The FEED phase (front end engineering design) starts immediately at Aibel’s headquarters in Stavanger and in Haugesund. The project will involve 45-60 people until delivery in June 2019.

The FEED contract is valued at around NOK 60 million.

The main objective of the project, Gudrun Phase 2 Water Injection, is to increase and extend recovery from the reservoir. In the FEED, Aibel will ensure maturation of the chosen concept for water injection into the reservoir. The contract includes study work related to new equipment and pipes for the water injection system. Additionally, Aibel will work on solutions for integration, hook-up and installation of this on the Gudrun platform.

The possible implementation phase has an estimated value of approximately NOK 400 million and will start immediately after conclusion of the FEED in the summer of 2019. In this phase, the project will involve around 160 people at its peak both onshore and on the installation offshore. Necessary fabrication will be carried out at Aibel’s yard in Haugesund.