SM58 G platform; Source: Byron

Byron Energy installs Gulf of Mexico platform

Project & Tenders

Oil and gas company Byron Energy has completed the installation of the SM58 G platform in the Gulf of Mexico.

SM58 G platform; Source: Byron

Byron said on
Monday that the installation of jacket and decks comprising the platform was completed.

The company
added that the Triton Hedron derrick barge de-mobilized off location after
installing the jacket over the SM58 G1 well drilled in October 2019, then
driving piles, and finally installing the topside facility.

Byron’s workers
are now living on the platform and are making final preparations to accept the
drilling rig which is scheduled to arrive in two weeks.

It is worth
noting that the company deployed a used and refurbished facility for the
project. According to Byron, it saved between $8-10 million and expedited cycle
time to first production by 9-12 months, compared to a newbuild facility.

The company
further stated that the next phase of the SM58 project was laying of the oil
and gas sales pipelines needed to transport produced hydrocarbons to market.

The pipeline
lay barge was mobilized on 3 July and arrived on location the following day.
Initial operations comprise the installation of the 4-inch diameter 305-meter
oil sales line.

Byron stated that once the oil line portion of the project was complete, the barge would begin laying the 8-inch diameter 12-kilometre gas sales line. Pipeline laying and tie-in operations are expected to take approximately 50 days depending on weather conditions.

As for the
rig, the Enterprise 264 jack-up drilling rig is scheduled to mobilize to the SM58
G platform by July 20, and begin completion operations on the G1 well.

Without significant weather delays, first production from the G1 is expected by 1 September 2020.