Iran: IOEC Loads Out P4 Jacket for Reshadat Field

The load out operation for Reshadat field’s P4 jacket started on Wednesday 27, April 2011 at around noon and ended the following morning at 2:30 a.m. on Thursday.

According to IOEC Public Relations Department the dimensions of P4 and its weight of 3200 Mt makes it an exceptional Jacket. The jacket was built by IOEC affiliated company, Tasdid.

 

The load out was made by FLB 129 and the installation of the jacket will be performed by Sadaf 3000 vessel.

After sea fastening operations FLB 129 will leave the port and reach its destination after 3 to 5 days.

The installation operation will be performed as a launch operation and it is estimated that the pile driving operation will conclude 40 days after the installation.

[mappress]

Source:IOEC , May 2, 2011;