Qatar: Rasgas Plans Three LNG Train Shutdowns

Rasgas Plans Three LNG Train Shutdowns

Qatari liquefied natural gas producer RasGas plans three maintenance shutdowns in 2013, Bloomberg informs.

The company’s fourth train will halt in April, while train 3 will be shut in September and unit 7 will undergo repairs in November. The repairs will last about three to four weeks.

RasGas oversees and manages all the operations associated with seven LNG trains and it has a total production capacity of approximately 37 million tonnes per annum.

[mappress]

LNG World News Staff, January 16, 2013; Image: RasGas