French oil major Total may face prosecution over the 2012 gas leak incident at its Elgin field platform in the UK part of the North Sea, 240 km from Aberdeen.

Total faces prosecution over Elgin gas leak

According to the British media, the UK Health and Safety Executive has filed the final report on the incident to the Scotland’s Crown Office for review, recommending prosecution.

To remind, production from the field was shut down on March 25, 2012, following a gas leak on the G4 well at the Elgin field, forcing Total to evacuate 238 people from Elgin and an adjacent drilling rig, the Rowan Viking. The incident occurred during work to plug and abandon the well, which was no longer producing gas.

“The report recommends proceedings are taken against the company for breaches of the Health & Safety at Work Act and the Offshore Installations and Wells Regulations,” the Wall Street Journal has quoted a Total spokesman as saying.

It took Total almost two months to plug the leak. The leak was stopped on May 15 after mud was injected into the well. The well was then permanently plugged with five cement plugs, the last of which was set in place on October 22, 2012, creating a 1,000-meter thick barrier.

On March 9, 2013, almost a year after the incident, production resumed at the Elgin/Franklin area, in the British North Sea.

 