Total Inaugurates Pazflor (Angola)

Total Inaugurates Pazflor

The giant Pazflor development, which lies 150 kilometres offshore Luanda in Angola, was inaugurated today at a ceremony attended by José Botelho de Vasconcelos, Angola’s Minister of Petroleum, Manuel Vicente, Chairman and CEO of Sonangol, Christophe de Margerie, Chairman and CEO of Total, Yves-Louis Darricarrère, President of Exploration & Production at Total; and representatives of Total and the local authorities.

We are very proud to be inaugurating Pazflor today. With this bold project, Total has pushed back the boundaries of technology. I would like to congratulate all of our teams for making it possible to successfully complete one of the world’s most outstanding oil developments. I would also like to thank our concession holder Sonangol and our partners for their support. Following on from Girassol and Dalia, Pazflor is a new chapter in the remarkable twinned story of Total, its contractors and Angola, allowing us to successfully pursue the Block 17 adventureChristophe de Margerie commented during the ceremony.

The field came on stream on the 24th of August. Output will reach 220,000 barrels per day and will make Total the leading oil operator in Angola and the African deepwater industry. This position should be cemented when the CLOV project begins production, scheduled for 2014.

Sonangol is the concession holder for Block 17, which is operated by Total E&P Angola, a wholly owned Total subsidiary, with a 40% interest. The other partners are Statoil ASA (23.33%), Esso Exploration Angola (Block 17) Limited (20%) and BP Exploration (Angola) Ltd (16.67%).

Pazflor facts and figures: a people-led technological feat

As many as 4,500 people on four different continents were involved in the project at the same time, for a total of 32 million hours worked, including 3.6 million in Angola. The global investment was approximately $9 billion.

At 325 metres long and 62 metres wide and weighing 120,000 tons, the Pazflor FPSO is the world’s largest floating production, storage and offloading vessel. Held in position by 16 subsea mooring connectors, the FPSO can store up to 1.9 million barrels in its hull and accommodate a total of 240 people.

A water depth of up to 1,200 metres and an aggregate depth of 2,700 metres.

The gigantic subsea gathering system covers 600 square kilometres, six times the area of Paris.

With 49 wells, 180 kilometres of flowlines and 10,000 tons of equipment on the seabed, the system is remarkable not only for its size, but also for its technical complexity.

Pazflor’s 590 million barrels of proved and probable reserves make it an “elephant”.

Pazflor milestones: the history of a giant

2000: The Pazflor adventure begins with the discovery of the Perpetua field, the first of the four ones that make up Pazflor. This discovery is yet another exploration success for Total in Block 17.

2002-2003: discovery the three other fields, Hortensia, Zinia and Acacia.

December 2007: Total launches development of Pazflor.

March 2009: first development wells drilled.

Summer 2010: installation of the subsea equipment begins. The process takes a year and at times requires up to 6 pipe-lay vessels and 40 support vessels.

January 18, 2011: the FPSO departs its South Korean shipyard for Angola, a journey of more than 20,000 kilometres.

August 24, 2011: Pazflor comes on stream several weeks ahead of schedule and on budget.

September 3, 2011: the first subsea separation unit is successfully commissioned, a world first.

Subsea separation, a world technological first

A key technical challenge is to produce two very different grades of oil from four distinct fields: Perpetua, Hortensia and Zinia (reservoirs of Miocene age) and Acacia (reservoir of Oligocene age).
Producing the heavy, viscous oil from the three Miocene reservoirs, which account for two-thirds of the reserves, and the related fluid flow requirements represents a major technological challenge. The gas has to be separated from the liquids on the mudline so that the viscous liquids can then be pumped to the surface.

The design and installation of subsea gas-liquid separation and pumping units on this scale constituted a world first. The pumps were purpose designed, tested and fabricated for Pazflor.

[mappress]
LNG World News Staff, November 22, 2011