VIDEO: Gorgon LNG project nearing completion

Chevron-operated Gorgon LNG project execution activities have reached the 90% mark.

All the subsea pipelines, wellheads and associated facilities for Gorgon and Jansz-lo fields are completed, the company said in a statement. All 18 subsea wells have been drilled and are complete, with pre-commissioning activities are under way on the subsea facilities at both fields.

Delivery of modules required for LNG Train 2 on Barrow Island off the Pilbara coast of Western Australia continues. All Train 1 modules and 13 of 17 Train 2 modules are on their foundations.

With permanent power to the permanent operations facility, the first members of the operations team have started commissioning and monitoring systems in the central control room. Construction and pre-commissioning activities are complete for one of the four ground flare boxes.

Both LNG tanks are ready for LNG and the construction is complete on three of the four condensate tanks.

The jetty is complete except for the loading arm installation. The domestic gas pipeline is now connected from the mainland through the jetty to the plant site and pre-commissioning activities are complete.

The company released a video update highlighting the progress made on the project, which is developing the Gorgon and Jansz-Io gas fields, located within the Greater Gorgon area, between 130 and 220 kilometers off the northwest coast of Western Australia. Included are the construction of a 15.6 million metric ton per annum liquefied natural gas plant on Barrow Island and a domestic gas plant with the capacity to supply 300 terajoules of gas per day to Western Australia.