Wind Turbine Installation Half Done at Trianel Wind Farm Borkum

Wind Turbine Installation Half Done at Trianel Wind Farm Borkum

Wind turbine installation at the Trianel’s wind farm off Borkum is halfway done, as 20 of the total 40 Areva’s turbines have been installed.

The installation of AREVA’s M5000 turbines began in September 2013. Located 45 kilometers off the German coast, the Trianel Wind Farm Borkum covers an area of 56 km². This wind farm will produce its first megawatt-hour of wind power this year.

“The AREVA’s proven technology and his experience in the installation of wind turbines give to the group undeniable credibility and know-how,” said Louis- François Durret, AREVA Renewables CEO.

He added: “This new milestone offers to AREVA an advantage which will be particularly profitable for the French offshore wind tender where AREVA has been selected as turbine supplier by the GDFSUEZ/EDPR/Neoen Marine consortium.”

By year-end, AREVA will have installed 120 offshore turbines in Germany providing electricity to around 600,000 households.

[mappress]

Press release, February 21, 2014; Image: trianel-borkum