The US$34 billion Ichthys LNG project in Australia, operated by Inpex, has recently lifted the roof of its second cryogenic storage tank at Bladin Point near Darwin.
The 90 metre span, 1100 tonne steel structure was constructed on the tank floor and then raised using two powerful fans, Inpex said in a project update.
Inpex General Manager Construction Vince Kenny said lifting the roof to its final height of around 32 metres took just over five hours to complete and required only 0.3 PSI of air pressure.
The giant LNG project will use the same process to raise the roofs of two remaining cryogenic tanks at Bladin Point, including one propane tank and one butane tank.
More than 80 people were involved in the lift, including a team of 30 welders who ascended the tank to fix the roof to the outer walls, Inpex said.
Each of the project’s two LNG storage tanks will have a volume of 165,000 cubic metres and will stand 46 metres high and span 91 metres.
[mappress mapid=”17332″]
LNG World News Staff; Image: Inpex
List of related news articles
-
Posted: about 1 month ago
Saipem hired for FEED services on Ichthys LNG
Saipem has confirmed a contract award to conduct booster compression module FEED services for the In...
Posted: about 1 month ago -
Posted: about 1 month ago
Russia's first LNG bunkering vessel gets storage tanks
Russia’s Gazprom Neft said the construction of the country’s first LNG bunkering vessel ...
Posted: about 1 month ago -
Posted: 2 months ago
Inpex extends Ichthys gig for Solstad vessels
Solstad Offshore has received a contract extension from Inpex for the provision of two AHTS to suppo...
Posted: 2 months ago -
Posted: about 1 month ago
First Russian large-scale cryogenic pump tested at Yamal LNG
Russian independent LNG export player Novatek has successfully tested the first large-scale cryogeni...
Posted: about 1 month ago