Panama Canal Gets First Pacific Gate

The first gate for the new locks on the Pacific side of the Panama Canal was installed on January 19, bringing the Panama Canal Expansion Program to 85 percent completion mark.

This gate, located in what is known as lock head one, is the first of eight gates that will be installed in the new locks at the Pacific side of the waterway. The steel rolling gate is 8 meters wide, 57.6 meters long and 22.28 meters in height, weighing 2,300 tons.

‘Today’s installation marks an important step towards the completion of the Expansion Program,” said Panama Canal Administrator/CEO Jorge L. Quijano. ”This project will have an important impact on world maritime trade and will further position Panama as the logistic hub for the Americas.”

The installation of the gates for the new locks began in December 2014 at the Atlantic side, where two gates have already been installed.

Upon completion, the two new lock complexes will have a total of 16 gates, eight in the Pacific and eight in the Atlantic.