Scour protection installation coming up at Hornsea Three OWF site

Business Developments & Projects

Installation of scour protection on wind turbine foundation locations at the Hornsea Three offshore site in the UK is set to commence in mid-December.

The work will be undertaken by DEME using its rock installation vessel Flintstone, equipped with a fallpipe and flexible bucket system.

The vessel is expected to mobilise from Jelsa Quarry, Norway, on December 13 and start installation on December 15. Operations are expected to be completed by the end of March 2026, according to a Notice to Mariners issued by Ørsted.

Currently, cable installation pre-lay operations are ongoing at the eastern part of the offshore wind farm’s export cable route, conducted by Jan De Nul using the vessel Pedro Alvares Cabral, with boulder and debris relocation along the inter-array cable (IAC) routes and foundation positions set to start soon. The work on the IAC routes will be carried out by Seaway7 and Helix using the vessels Normand Subsea and Grand Canyon III.

Ørsted took the final investment decision (FID) on Hornsea Three offshore wind farm in 2023, after the company was awarded a contract for difference (CfD) for the 2.9 GW project in July 2022.

This November, Ørsted entered into an agreement with Apollo-managed funds (Apollo) for a 50% equity ownership share in Hornsea Three for approximately DKK 39 billion (about €5.2 billion).

Located 160 kilometers off the Yorkshire coast, the Hornsea Three offshore wind farm will feature around 200 Siemens Gamesa 14 MW wind turbines and is expected to be operational in 2027.

OE logo

Power Your Brand With Offshore Energy ⤵️

Take the spotlight and anchor your brand in the heart of the offshore world!

Join us for a bigger impact and amplify your presence at the core hub of the offshore energy community!