Tempo Australia adds variations to Gorgon LNG contract

Mining and energy sector services company, Tempo Australia informed that it has secured new contract extension variations for the giant Gorgon LNG project totalling approximately $50 million.

Tempo unit, Tempo Construction and Maintenance, has won variations to its existing sub-contract at Chevron’s USD 54 billion Gorgon LNG project on Barrow Island, Western Australia.

The variations relate to the provision of Managed Structural, Mechanical and Piping, Electrical & Instrumentation craft labour for construction, pre-commissioning and commissioning services to the Mechanical, Electrical and Instrumentation contractor on the Gorgon LNG project, the company informed in a statement.

Tempo has also been awarded an extension to its existing contract with Rio Tinto at its 353Mtpa Cape Lambert Port B expansion project, in the Pilbara region of WA.

[mappress mapid=”17639″]

Image: Chevron