UK: Flare at Elgin Platform Could Ignite Gas Cloud, Experts Say

 UK: Flare at Elgin Platform Could Ignite Gas Cloud, Experts Say

The gas leak that occurred at the wellhead platform on the Total-operated Elgin field in the UK North Sea, remains ongoing, the operator reports.

The gas has been flowing since Sunday, March 25th, when Total evacuated all the personnel from the Elgin platform. The precise cause of the gas leak, that has been flowing approximately 240 km east of Aberdeen, is yet to be identified.

According to The Telegraph, experts have warned that the gas cloud which can be seen is very flammable and they described the situation as a disaster waiting to happen because the flare on the Elgin platform is still ongoing.

Total explains that the flare is an integral part of the platform’s safety system, and it is used to safely evacuate all the remaining gas from the platform.  The company says that the flare does not pose a threat, because the winds are taking the gas cloud away from the open flame.

“The wind is forecast to remain in its current direction for the coming days.  You can be assured that this is being reviewed on a constant basis and should this change any impact is being assessed.  In parallel we are investigating solutions to extinguish the flare if it does not burn out by itself.”

Elgin and Franklin are two high pressure/high temperature gas and condensate fields in the Central Graben Area of North Sea. Total E&P UK Limited owns 46.17% and is operator of both fields through its wholly-owned subsidiary EFOG and its average share of production was around 60,000 barrels of oil equivalent per day in 2011.

Elgin/Franklin facilities comprise two wellhead platforms, one on Elgin and one on Franklin and a Production/Utilities/Quarters (PUQ) platform. The PUQ is on the Elgin field and is linked to the Elgin wellhead platform by a 90-metre bridge.

[mappress]
Offshore Energy Today Staff, March 29, 2012