USA: Corps Announces Mississippi River Dredging Plan

Corps Announces Mississippi River Dredging Plan

U.S. Army Corps of Engineers has announced a plan for the Mississippi River dredging project.

The work will consist of placing hydraulically dredged material taken from a borrow area located on the river bottom.

Maximum height of the sill will be the point at which the settled dredge material at the disposal area reaches a maximum height of -45 feet NGVD along the entire length of the sill.

The estimated time for the completion is 89 calendar days. The estimated value of this work is between $5,000,000.00 and $10,000,000.00.

The solicitation for this development program will be issued on or about 11 April 2013.

More info

[mappress]

Source: fbo.gov, March 28, 2013