Wintershall hands in Skarfjell concept, enters next project phase

Wintershall Norge has now submitted the development concept for the Skarfjell field development, located in the Norwegian sector of the North Sea, to the Norwegian Ministry of Petroleum and Energy.

Wintershall, together with its license partners Capricorn, Bayerngas, Edison and DEA, recently selected a development solution for the Skarfjell field. Under the proposed solution, the reservoir will be connected to the nearby Gjøa platform via a subsea tie-back.

Skarfjell is situated in the northeastern North Sea approximately 20 kilometers southwest of the Engie-operated Gjøa platform and about 130 kilometers northwest of Bergen. Skarfjell is expected to yield between 60 – 140 million barrels of oil equivalents.

Wintershall said on Wednesday that the license partnership now enters the define phase of the project, refining the technical and economic plan before committing to a final investment decision.

Martin Bachmann, Wintershall’s Executive Board Member for Exploration and Production in Europe and Middle East, said: “Moving into the next phase of the plan is a signal that Wintershall is committed to Norway in the long-term. This is our second operated development project on the Norwegian Continental Shelf after Maria, and we are using our experience and resources to fine-tune the concept for Skarfjell. Wintershall is convinced of having selected the most economically robust solution for the field. We will now work closely with our partners in the coming months to design a plan that will take Skarfjell forward.”

 

Using existing infrastructure

 

Based on the proposed plan, hydrocarbons from the Skarfjell reservoir will be developed with two subsea templates tied back to the Gjøa platform for processing and export. Gjøa will also provide lift gas to the field and water injection for pressure support.

Bernd Schrimpf, Wintershall Norge Managing Director, said: “Reaching this stage in the development has required a thorough technical and commercial investigation into various development solutions for Skarfjell. By deciding with our license partners to pursue a tie-back to existing infrastructure as our preferred option, we believe we have found the best way of unlocking the maximum value from the field. In this way Skarfjell could provide substantial returns for Wintershall, our partners and the rest of Norwegian society.”

Wintershall added that several studies will now be conducted before the final investment decision and the plan for development and operation (PDO) can be submitted to the Ministry of Petroleum and Energy.