PA Resources AB completed installation of new Didon platform

PA Resources AB (publ) has completed the offshore installation of the entire platform incl. the main deck and flare boom in the Didon field in Tunisia. Subsequently, the company will shortly start to drill the first production well, Didon#5.

PA Resources AB has now fully completed the offshore installation of the platform on the Didon field. (See picture.)

As communicated earlier this month, the company previously completed the jacket installation and the mounting of the first of two decks, the cellar deck. Since then the first deck has been secured to the jacket and installation of three conductor pipes have been completed. The conductors are installed along the jacket and into the soil and will become the guides to the platform wells to be drilled into the Didon reservoir. Further the installation of the main deck and the flare boom has successfully been completed.