TGL EMEC base removal (Courtesy of Colin Keldie)

Partners share tidal energy tripod’s decommissioning know-how

A collaborative decommissioning project at the European Marine Energy Centre (EMEC) has completed the forensic analysis of a tidal energy tripod.

TGL EMEC base removal (Courtesy of Colin Keldie)
TGL EMEC base removal (Courtesy of Colin Keldie)
TGL EMEC base removal (Courtesy of Colin Keldie)

The study gained a comprehensive understanding of the end-of-life condition of the tripod, assessing the long-term effect of deploying components and systems in the challenging high velocity environment at EMEC’s Fall of Warness tidal energy test site.

The tripod had been submerged for approximately 11 years during which two tidal turbines had operated on it.

Significant learnings have been collated and two reports published to provide feedback and design guidelines to the offshore renewable energy industry, enabling developers to minimise decommissioning costs and de-risk future projects, according to EMEC.

The first report highlights supply chain lessons regarding the tools required to cut and lift the tripod from the seabed in high tidal currents, while the second report focuses on learning for the design and manufacture of the foundations themselves with regard to biofouling, corrosion and metals.

John Skuse, Operations and Maintenance Manager at EMEC, said: “Decommissioning is a critical part of the lifecycle of ocean energy projects, however it’s not yet well explored, as relatively few ocean energy technologies have progressed to the decommissioning stage following long-term deployment.

“It is imperative that decommissioning is managed carefully, including design stages, installation, performance, right through to decommissioning. As the industry continues to develop and mature, the ability to decommission devices efficiently and cleanly will be instrumental in ensuring site utilisation is maximized”.

EMEC contracted Orkney-based marine operations provider, Leask Marine, to remove the tripod foundation from the Fall of Warness test site.

Photo showing workers during cutting and retrieval operations (Courtesy of Colin Keldie)
Workers during cutting and retrieval operations (Courtesy of Colin Keldie)

The project required continuous innovation by the Leask Marine team during the cutting and retrieval operations. Standard industry equipment used in offshore subsea oil and gas would have been unable to withhold the strong currents.

Leask Marine’s engineering team therefore designed and fabricated a new robust cutting tool support frame to hold the tool in place on the pile with sufficient grip to control the turbulent drag forces.

The specifically designed frame had a buoyancy system added to help lift the 140-ton structure from the seabed in one operation. Leask Marine’s vessel then towed the frame and tripod to Hatston Pier in Kirkwall for forensic analysis, final cutting and disposal of parts.

Forensic analysis of a tidal energy tripod

Forensic analysis was carried out by Blackfish Engineering Design, the International Centre for Island Technology (ICIT) at Herriot Watt University, Rovco , Brunel Experimental Techniques Centre, and Brunel Centre for Advanced Solidification Technology.

Forensic examination activities assessed biofouling, corrosion, metallurgic (metal) defects and electrical connector longevity.

Photo showing the lifting of the tripod (Courtesy of Colin Keldie)
The lifting of the tripod (Courtesy of Colin Keldie)

The study found that all surfaces exposed to seawater current will be subjected to vigorous fouling. Components that are expected to move, slide, or require clearance in any way must be designed assuming that biofouling will occur on all steel surfaces

Components that are installed for long-term submersion should be designed to account for biofouling end stage communities up to 15 centimetres thick and the additional weight should be factored into lifting operations during decommissioning, the study found.

Biofouling was markedly reduced where larvae access to surfaces was restricted due to a lack of flow and a lack of nutrient supply.

Stainless steel 316L, titanium and super duplex material have all shown excellent resistance to corrosion, but all of them are susceptible to biofouling, according to the findings.

The full lessons learned report has been published highlighting best-practices for device and infrastructure design, deployment, operation, maintenance, and decommissioning.

Tim Warren, Engineering Director at Blackfish, said: “This decommissioning project has provided really valuable data for engineering designers and project developers of offshore renewable devices. A detailed examination of the biofouling, corrosion and performance of different structures, materials and coatings has provided a great insight into the long term performance of submerged components and how the design can be improved to ensure longevity and performance for their entire lifetime.

“By publishing this project and the lessons learned to the wider offshore renewables industry, it is hoped that future devices will benefit from this by reducing costs and improving decommissioning operations”.

Douglas Leask, Managing Director of Leask Marine, added: “The decommissioning of TGL tripod has been an excellent project for Leask Marine by utilising the full resources of the business, from marine consultancy, detailed engineering, procurement, fabrication, vessel charter, commercial diving, and using the latest subsea technologies. The whole project was a positive experience in decommissioning subsea structures safely and cost effectively.

“This decommissioning project has been a real learning exercise on creating customer value and lowering costs for the decommissioning of large subsea assets in the industry. This knowledge base allows future developers accessible operational tooling that can meet the challenges ahead in the decommissioning of future offshore renewable energy arrays”.

The study was conducted as part of the EMEC-led FORESEA project, funded by Interreg North-West Europe.