PSA Norway: Serious breach of regulations at Statfjord C

The investigation of the hydrocarbon leak of 26 January 2014 on Statfjord C platform by the Petroleum Safety Authority Norway (PSA) identified serious breaches of the regulations. Operator Statoil has now been notified of an order by the PSA.

PSA Norway Serious breach of regulations at Statfjord C

The hydrocarbon leak occurred while stabilised oil was being transferred from Statfjord A to Statfjord C in the Norwegian part of the North Sea.

At the same time, preparations were being made for maintenance work on a loading pump in the shaft. An isolation valve for the pump sprang a leak, causing the pump house to fill with oil. This oil drained to the sump tank at the base of the shaft via an open drain valve. When the level in the sump tank reached 70 per cent, the pump for transferring liquid from the sump tank to the oily water tank beneath the cellar deck started up. The valve controlling the level in the oily water tank failed to open, and oil escaped via fire seals on the cellar deck.

Consequences
Statoil calculated that up to 42 cubic metres of stabilised oil escaped in about 37 minutes, at a leak rate of 20.8 kilograms per second. Forty cubic metres are estimated to have spilt to the sea, while two cubic metres dispersed over the installation.

There were 270 people on the installation, and no personal injuries have been reported as a result of the incident. Production was shut down for almost four days owing to the leak.

Potential consequences

Potential consequences in the event of ignition are assessed to be a possible spray fire or combustion of oil drops/flowing oil for the duration of the leak.

In addition, the probability for a repetition of similar leaks was high immediately after the incident.

Investigation
The PSA resolved to investigate the incident.

Nonconformities
Six nonconformities were identified by the investigation. These related to:

  • the original design solution for the drainage system
  • the modified design solution for the drainage system
  • consequence classification of the open drainage system
  • preparations for maintenance
  • management of simultaneous activities
  • qualification and follow-up of contractor expertise.

Improvement points
Four improvement points were also identified. These include critical comments from the PSA concerning parts of Statoil’s own investigation concerning classification of the leak, its potential consequences and a failure to address the underlying causes of the incident adequately.

On the basis of the findings of its investigation, the PSA has given Statoil notice of the following order:

“Pursuant to section 69 of the framework regulations on administrative decisions, see section 21 of the management regulations on follow-up, Statoil is ordered to review its system for following up and identifying the reasons why the technical, operational and organisational weaknesses, faults and deficiencies which have been identified, see chapter 6.1 of the report, have not been identified, and to implement the necessary measures.

The deadline for compliance with the order is 1 October 2014.”

An order is an administrative decision made pursuant to the regulations. Before the PSA issues an order, it usually submits a notification of order to the companies involved. An order is a powerful preventive measure and legally binding on the recipient.

[mappress]
Press Release, August 11, 2014