Statoil: Damaged pipe shuts down Troll C production

Statoil has shut down production on the Troll C platform in the North Sea on Sunday 17 August after an inspection programme on the platform detected corrosion damage to a pipe connected to the oil export system.

Troll C platform

The corroded pipe will be replaced. This is expected to require a 7-day shutdown.

Troll CTroll C has a daily equity production of some 58 000 barrels of oil , and exports 8 million cubic metres of gas. In addition, some 34 000 barrels of oil and 2 million cubic metres of gas are transported from the Fram field through the Troll C platform.

 

[mappress]
Press Release, August 20, 2014