Delivery of INS Vikramaditya Rescheduled

Delivery of INS Vikramaditya Rescheduled

As informed by the Russian side the delivery of the aircraft carrier INS Vikramaditya (Gorshkov), after completion of repairs and sea trials, would be made in the last quarter of 2013.

The aircraft carrier was subjected to extensive trials for the first time for 108 days from 8th June 2012 to 23rd September 2012, with a part of the Indian crew on board, undergoing training during the sea trials. While a substantial scope of ship’s equipment and aviation trials were completed during this period, the main propulsion plant trials to full power could not be completed due to defects encountered on boiler section. Rectification of the defect is likely to take six months.

Liquidated Damages (LD) clause for delays in delivery is incorporated in the contract. As per contract, LD is to be ascertained and levied within six months of ship’s delivery.

The Russian side has been requested to take up necessary measures to ensure delivery of ship in the last quarter of 2013.

INS Vikramaditya has a displacement of 45,000 tons, and an endurance of 13,500 nautical miles (25,000 km) at a cruising speed of 18 knots. It will have an air wing consisting of Russian-made MiG-29K jet fighter planes and Kamov Ka-31 early warning radar helicopters.

[mappress]
Press Release, December 12, 2012