Largest Number of Turbines Installed at Gwynt y Môr (UK)
On 19 January 2014, turbine no. 112 was installed on Gwynt y Môr in the Irish Sea.
This is the largest number of turbines ever installed on one single project by A2SEA. Prior to this, A2SEA installed 111 turbines on Anholt Offshore Wind Farm in 2013.
Work continues and SEA JACK and SEA WORKER are installing the rest of the 48 turbines together.
Scope of work: 160 Siemens 3.6MW
[mappress]
A2SEA, January 27, 2014
Related news
List of related news articles
-
Posted: 2 days ago
OHT opening turbine installation headquarters in Denmark
Norway-headquartered OHT is launching a new office in Denmark as the base for its operational and co...
Posted: 2 days ago -
Posted: 3 months ago
RWE signs lease agreements for four UK offshore wind extensions
RWE and its project partners have signed lease agreements with The Crown Estate to develop extension...
Posted: 3 months ago -
Posted: 7 months ago
Modus’ HAUV-2 wraps up Gwynt-y-Môr depth of burial survey
Modus Seabed Intervention has completed a high speed bathymetric and depth of burial survey of the i...
Posted: 7 months ago -
Posted: 18 days ago
Moray East wind turbine installation to start soon
Wind turbine installation at the Moray East offshore wind farm is scheduled to start in the first da...
Posted: 18 days ago