World’s first maritime megawatt charging system picked for AT’s electric ferries

Swiss technology company ABB has secured a contract with Auckland Transport (AT), New Zealand’s transport services and infrastructure provider, to deliver the maritime industry’s first megawatt charging system (MCS) for all-electric and hybrid-electric ferries.

EV Maritime Auckland Transport

The shore-to-ship charging system uses an interface common to trucking and aviation and is expected to lower market barriers to entry for electric ships.

As part of its Mission Electric initiative, AT has ordered two 200-seat all-electric ferries and two 300-passenger hybrid-electric ferries and is expected to become the largest electric ferry fleet operator in the Southern Hemisphere by 2030.

Replacing conventional, diesel-operated ferries, the new ferries are estimated to help AT cut diesel use by 1.5 million liters, and CO2e emissions by 4,000 metric tons per year, equivalent to the annual emissions generated by about 90 diesel buses.

“It is incredibly exciting to lead the way with modern, low-emission public transport,” Nathan Cammock, Programme Director, Auckland Transport, said.

“Our new Auckland-owned ferries will bring greater passenger capacity, improved accessibility and a more consistent customer experience. They will rely on modern charging infrastructure to deliver on these capabilities.”

While ferries carry only six percent of public transport users in Auckland, their diesel engines produce 20 percent of the city’s public transport greenhouse gas emissions. New Zealand has set decarbonization goals by including a 2050 net-zero emissions target in its Zero Carbon Act. Given its responsibility for public transport infrastructure around the Hauraki Gulf, AT has chosen to electrify its ferry network using the CharIN megawatt charging system standard.

Specifically, ABB will work with local partners to deliver, engineer and install five complete charging solutions during 2024 and 2025 at several ferry terminals. Each system will feature a pair of 1.65MW chargers, consisting of a transformer, ACS880 converters, MCS plugs and cable management on the ferry pontoons. The chargers will deliver over three megawatts of direct current (DC) power to sustain the short turnarounds and high-power demands needed to maintain an efficiently operated ferry fleet.

The connectors will be handled by crew during passenger turnarounds. The Auckland installation will also be the first MCS supplied by ABB to benefit from the standardized plug-in interface, although the group has been delivering shore-to-ship power for over 20 years since an initial contract with Princess Cruises in Alaska.

The Auckland solution will be similar in charging capacity to ABB’s landmark project to support 10 all-electric ferries for public transportation provider Transtejo Soflusa in Lisbon, Portugal.

“Ferries connect communities and have a significant impact on the environment,” Palemia Field, Ferry Segment Manager, ABB Marine & Ports, said.

“There’s a well-known Māori proverb which says ‘ka pū te ruha, ka hao te rangatahi’, or ‘once the old fishing net is worn, it is put aside to make way for the new fishing net’. Electrification is crucial and we must move away from emissions-generating technologies. Noise- and emission-free operations benefit both the broader and local communities, while passengers onboard enjoy improved travel comfort thanks to less vibration.”

As the electrification of the global ferry fleet increases, ABB expects more operators to opt for a standardized interface that is familiar from other industries.

Electric ferry orders made up 37 percent of the maritime battery capacity deliveries between 2019 and 2022, according to research published by IDTechEx2. A 2023 forecast from Spherical Insights3 suggests that the market for all types of electric ships will double in value by 2030 over a 2021 baseline, to surpass $10.5 billion.