10000 results found for 'progress'

10000 results found for 'progress'
Order results by

A list of search results

  • 25 February 2022
    Authorities & Government, Business Developments & Projects, Collaboration, Market Outlooks, Outlook & Strategy, Regulation & Policy

    Swedish-Israeli company Eco Wave Power has welcomed the ambassador of Portugal to Israel Jorge Cabral on a site visit to the EWP-EDF One wave energy project being developed in Israel.

  • 17 May 2019

    The Dutch maritime technology sector saw its activity rise slightly in 2018.

  • 8 August 2011

    Gdańsk Shipyard restructuring program is in the halfway, so is the investments’ plan. The main idea of this program is to base of the company`s production on three pillars: shipbuilding, large-size steel constructions and wind towers. The shipyard has already made some steps in the new sectors: the first steel constructions (girders) for the new […]

  • 22 August 2013

    Rosneft and ExxonMobil continue to progress the LNG project proposed in the Russian Far East. The contractor selection process for design and engineering work has officially commenced. In 2013-2014 Rosneft and ExxonMobil plan to complete design work, including selection of a liquefaction technology and identification of major equipment requirements, to perform engineering surveys, develop Front […]

  • 27 April 2012

    Svitzer salvors have made good progress in removing containers and cargo from Rena throughout the week. Dive operations to remove smaller pieces of debris and cargo have been undertaken. Divers are cutting into parts of the submerged stern section to gain access to containers for removal. There are currently moderate to strong winds and swells […]

  • 20 September 2011
    Business & Finance

    The Security Association for the Maritime Industry (SAMI) welcomes the IMO’s progress on its revised guidance and recommendations for the use of privately contracted armed security on-board ships. Following last week’s Intersessional Maritime and Piracy Working Group, the IMO has released new guidance and recommendations on the use of privately contracted armed security personnel. SAMI […]

  • 24 December 2010
    Business & Finance

    Bounty Oil & Gas NL  announces progress report on the New Seaclem 1 well in PEP 11, offshore NSW. MEC Resources  investee company Advent Energy Ltd (Advent) has reported: Progress since Last Report The well was spudded at 00.00 hours AEDST 15 December 2010 and drilled the 9 7/8″ pilot hole to 310.5 metres BRT. […]

  • 3 August 2010
    Equipment, Project & Tenders

    Construction of the second cylindrical ultra-deep water Semi-submersible Drilling rig SEVAN DRILLER II, being built for Sevan Marine ASA, is progressing steadily and on schedule in COSCO Nantong Shipyard. The 13.4m stage block erection of the main hull is nearly complete and three levels of the accommodation block have been completed. Work on installation of […]

  • 13 March 2025
    Carbon Capture Usage & Storage, Infrastructure, Vessels

    Royal Wagenborg, a Netherlands-based shipowner and operator, has revealed a ‘crucial’ progress update on the construction of what is being hailed as “the world’s first CO2 carrier.” As disclosed on March 11, 2025, the aft ship, which houses the main engine and other essential systems, has been transported at the local shipyard Royal Niestern Sander, […]

  • 18 August 2011

    Fabrication is progressing on the 14.95m Scalloper under construction at Macduff Shipyards. Macduff Ship Design have provided all construction plans and cutting information for this new build. The company uses the latest in Computer Aided Design (CAD) software packages to produce all their construction, outfit and concept drawings for new builds and conversions. The electronic […]

  • 11 November 2011
    Business & Finance

    Good progress continues to be made in removing the last of the oil from the submerged number 5 starboard fuel oil tank on the grounded container ship Rena, Maritime New Zealand (MNZ) says. MNZ Salvage Unit Manager Arthur Jobard said salvors had maintained continuous pumping of heavy fuel oil from Rena to the tanker Awanuia […]

  • 3 February 2014
    Business & Finance, Research & Development

    The Australian and Queensland Governments have released the 2014 State Party Report on the Great Barrier Reef World Heritage Area which highlights the significant progress being made to improve the management, health and protection of this amazing iconic area. This progress report has been delivered to the World Heritage Committee meeting currently underway and demonstrates […]

  • 5 August 2025
    Business Developments & Projects, Collaboration, Outlook & Strategy, Transition

    Italy’s engineering, drilling, and construction services giant Saipem has become an associate member of Nuclear Energy Maritime Organization (NEMO), an organization focusing on the practical application of new nuclear solutions in the maritime industry.

  • 23 June 2025
    Business Developments & Projects, Project & Tenders

    Japan’s JERA, an equal joint venture of two major Japanese electric power companies, TEPCO Fuel & Power Incorporated and Chubu Electric Power Company, has signed a non-binding heads of agreement (HoA) with the Singaporean subsidiary of of Australian energy giant Woodside for the purchase of liquefied natural gas (LNG) from the latter’s portfolio.

  • 20 December 2011

    The progress on Walney 2 has been dramatically reduced due to windy weather conditions for the last couple of weeks. Heavy winds and high waves have paused the commissioning activities at Walney 2, making it impossible to access the turbines. When the wave height exceeds certain limits, all personnel transfer to the turbines is stopped […]

  • 24 August 2020
    Vessels

    The sinking of the bow section of the broken up bulker Wakashio off Mauritius, launched on August 21, is progressing slowly but surely as weather conditions continue to hamper the operation. It usually takes around 24 hours for a vessel’s front section to be completely immersed, however, due to rough sea conditions the sinking had […]

  • 25 May 2011

      Eastern Star Gas Managing Director David Casey Discussed Narrabri CSG Project progress with Openbriefing.com: Eastern Star Gas Limited has five production pilots in operation across the Narrabri CSG Project. These include the Tintsfield pilot, which commenced operation in April, targeting the Hoskissons coal seam. What is the importance of this for your gas reserves […]

  • 24 February 2014

    In January 2014, Under Secretary of the Army Joseph W. Westphal met with leaders from the U.S. Army Corps of Engineers, North Atlantic Division and New York District to receive various updates regarding the Corps’ efforts post Hurricane Sandy and observe the significant progress of the New York and New Jersey Harbor Deepening Project. “Given […]

  • 29 July 2013

    Armour Energy announced good progress in the Egilabria 2 lateral well. The well is being drilled to test the reservoir characteristics and ascertain likely gas flow rates in a commercial development scenario for Armour Energy’s gas resources in the Lawn Shale unit of the Isa Superbasin, ATP 1087, north of the regional mining and infrastructure […]

  • 9 November 2022
    Business & Finance, Business Developments & Projects, Collaboration, Market Outlooks, Operations & Maintenance, Outlook & Strategy, Technology

    SIMEC Atlantis Energy has made ‘good progress’ in the delivery of its commercial-scale tidal energy array at MeyGen site in Scotland.

  • 20 September 2024
    Business Developments & Projects, Exploration & Production

    Japan’s shipping giant Mitsui O.S.K Lines (MOL) is to invest in U.S.-based e-fuels producer HIF Global through its wholly-owned subsidiary MOL Clean Energy aiming to reduce carbon emissions by promoting the establishment of a ‘robust’ e-fuel and CO2 supply chain. As informed, HIF Global has already laid the groundwork for the annual production of 4 […]

  • 15 December 2010
    Business & Finance, Project & Tenders

    Bounty Oil & Gas NL (“Bounty”) announces progress report on the New Seaclem 1 well in PEP 11. The well was spudded at 00.00 hours AEDST 15 December 2010 and has drilled the 9 7/8″ pilot hole to 310.5 metres BRT. Current operations: Preparing to open hole to 36″ before running the 30″ conductor casing. […]

  • 10 February 2012

    Construction work on Viking Line’s new passenger vessel NB 1376 is notably progressing at the STX Finland shipyard in Turku. The section 630 of this 214 m inspiring and exciting newbuild is currently being assembled. Delivery of the ice class 1 A Super vessel is expected in January 2013, and she will be the most […]

  • 10 April 2014
    Business & Finance, Equipment, Technology

    The U.S. Army Corps of Engineers and the New Jersey Department of Environmental Protection are currently evaluating several flood risk management alternatives for the Rahway River Basin, with the preliminary findings to be shared with area residents at two public information sessions to be scheduled in late May or early June 2014. Included in the […]

  • 10 February 2011

    Infrastructure work on a new container port next to Sri Lanka’s existing Colombo harbour that will expand capacity has neared the halfway… (lankabusinessonline) [mappress] Source: lankabusinessonline, February 10, 2011;