Tempo Australia adds variations to Gorgon LNG contract

Project & Tenders

Mining and energy sector services company, Tempo Australia informed that it has secured new contract extension variations for the giant Gorgon LNG project totalling approximately $50 million.

Tempo unit, Tempo Construction and Maintenance, has won variations to its existing sub-contract at Chevron’s USD 54 billion Gorgon LNG project on Barrow Island, Western Australia.

The variations relate to the provision of Managed Structural, Mechanical and Piping, Electrical & Instrumentation craft labour for construction, pre-commissioning and commissioning services to the Mechanical, Electrical and Instrumentation contractor on the Gorgon LNG project, the company informed in a statement.

Tempo has also been awarded an extension to its existing contract with Rio Tinto at its 353Mtpa Cape Lambert Port B expansion project, in the Pilbara region of WA.

[mappress mapid=”17639″]

Image: Chevron